Building Permits & Fees

Submit your building permit application by June 30, 2025 for a 50% building permit fee reduction.
To be eligible you need to be rebuilding on property that you owned on June 30, 2021.

Find information on this page about the following:

Building permit application requirements

You need to complete several forms as part of your application. These include Village of Lytton and third-party documents.

Village of Lytton documents

You will need to submit documents from the Village of Lytton, including the following:

See all Village of Lytton application forms

Third-party documents

You will also submit third-party documents with your application, such as the following:

  • Certificate of Title dated within 30 days of application
  • Property survey
  • Set of blueprints
  • Engineers' documents:
    • Schedule B: Letter of Assurance
    • Appendix E: Confirmation of Professional Liability Insurance
    • Certificate of Liability Insurance
  • Drawings sealed by the Professional Engineer

If you have any questions, contact the Building Department.

Print the Building Permit Application checklist

Apply using the Cloudpermit portal

The Village of Lytton uses Cloudpermit, a collaborative system for building permit applications, payments, and inspections. You will submit your application using this portal.

Learn how to use Cloudpermit

Log into Cloudpermit

Application fees

When you apply for a building permit, you will be required to pay the following:

Type of fee Cost
Building permit application fee $200
Refundable security deposit $250 for simple (Part 9) buildings
$500 for complex (Part 3) buildings

When you complete construction, the Village will refund your security deposit after an inspection if all public works (for example, water and sewer pipes) and land (like municipal roads) are in good condition.

Permit fees

When your building permit is issued, you will need to pay for the following:

Building permit fee

Building permit fees are calculated according to the total value of construction, as set out in Appendix B of Building Bylaw 710, 2022.

A 5% reduction of the building permit is granted when registered professionals are used for all or a portion of the permit, up to a maximum of $500.

Building Bylaw 710, 2022

Example

See an example building permit fee calculation for a home with a construction value of $500,000.

Plumbing permit fees

Plumbing fees are calculated based on how many of each of the following will be in the building:

  • Fixtures
  • Interceptors or catch basins
  • Backflow prevention device
  • Fire sprinkler system (per sprinkler head)

Fees are set out in Appendix B of Building Bylaw 710, 2022.

Refundable permit fee surcharge

The refundable permit fee surcharge is based on construction value as follows:

  • $50 where the construction value is less than $10,000
  • $200 where the construction value is between $10,000 and $50,000
  • $500 where the construction value is more than $50,000

The surcharge will be refunded if all work associated with your building permit is completed within 2 years of the building permit being issued.

Additional fees

Other fees may apply for the following:

  • Installation of a chimney
  • Demolition or relocation
  • Reinspection or special inspection
  • Double permit fee, if the work is started before the building permit is issued
  • Manufactured home or relocated building and its foundation
  • Permit renewals
  • Civic address sign
  • Temporary buildings
  • Permit application legal change
  • Major modifications to the permit design and construction

Fees are set out in Appendix B of Building Bylaw 710, 2022.