Twice daily Highway 12 closures at Texas Creek scheduled from September 8 to October 21, 2025

Type(s)
Partner Update

The Ministry of Transportation and Transit has provided updates about planned repairs to existing rockfall protection systems along Highway 12 at Texas Creek (also known as Big Slide), approximately 44 km north of Lytton (20 km south of Lillooet).

UPDATED SCHEDULE: Construction will take place from Monday, September 8 to Saturday, October 21, 2025.

Due to limited roadway width, Highway 12 at Big Slide will be closed twice daily during construction, to accommodate the equipment and personal necessary to complete the repairs.

Highway 12 at Big Slide – Access schedule

Closed:      8:00 am to 12:00 pm
Open:        12:00 pm to 1:00 pm
Closed:      1:00 pm to 5:00 pm
Open:        5:00 pm to 8:00 am

Construction and road closures will take place Monday to Saturday. No construction or road closures will take place on Sundays or Statutory Holidays. Highway 12 will only be closed at the Texas Creek project site. Once construction is complete, Highway 12 will be returned to normal conditions.

Highway 12 Texas Creek repair location map