The Village is repairing and replacing the water infrastructure on the east side of Main Street between 5th Street and 6th Street.
August 8, 2025
Next week the contractor will be moving through the entire site installing water services. Expect traffic disruptions. Local traffic will be accommodated with some interruptions and delays.
August 1, 2025
Construction work is continuing. This week 6th Street is closed to everything but local traffic (with delays). See the map below:
July 28, 2025 update
Contractors hit solid rock on Station Street today. While they wait for equipment to deal with this, they are moving over to begin work on 7th Street. 7th Street will be closed to everything but local traffic (with delays).
July 25, 2025 update
During the week of July 28 to August 1, there will be road closures (with local access only) on:
- Station Street from 6th to 7th Street
- 7th Street from Station Street to Alonzo Way
July 21, 2025 update
Station Road will be closed between 5th Street and 7th Street, except for local traffic. Please expect delays. See the map below:
July 10, 2025 update
During the next six weeks, there will be some intermittent road closures in the project area. See the traffic management plan below for the week of July 14, 2025 or download it.
Later during the project there will be excavations on Main Street, which will require single-lane alternating traffic to be coordinated with the Ministry of Transportation and Transit.
Project work is expected to take place seven days per week from 7 a.m. to 7 p.m.
July 7, 2025 update
Preliminary work will start on Monday, July 7, 2025. This consists of investigative excavations at five sites (indicated on the map with a black star).
There will be minor traffic disruptions with detours around the excavation sites, as needed.
Watermain construction work is expected to start on Tuesday, July 15, 2025. We will provide updates on traffic and construction impacts.