Find construction updates for Center Lane area: April 6 to 19, 2026

Type(s)
Sewer Notices and Updates
Village Update

Recently we shared information about the upcoming West of Main Street sewer main replacement.

Here are some construction updates for the Center Lane area:

April 6 to 11

Residents can expect to see:

  • Machinery and crews removing asphalt, locating existing utilities, completing as-built drawings on located utilities, and backfilling; and
  • Mobilization of equipment, including excavators, loaders, compactors, and materials.
     

April 12 to 19

There will be no thru traffic on:

  • 1st Street
  • Center Lane from 1st Street to Second Street

Activities will include relocating water services, if required, and installation of manhole, sewer main, and storm sewers.

Read the contractor's two-week construction update